GEDCo's Technical Achievements from August 1998 till 31 December 2010

 

Regardless of the difficult circumstances that faced the company like the lack of financial resources, the lack of electricity supply from Israel and the start of the Al-Aqsa Intifada, GEDCo management and staff faced all these difficulties and went forward to supply Gaza Strip with electricity by constructing hundreds of projects especially after the Gaza Power Plant started operating.

 

The projects implemented  by GEDCo from August 1998 until 31 December 2010 has been 3,969  projects as follows:

 

1. Implementation of minor and major projects:

·       GEDCo has implemented 565 of the major projects, which are projects for the installation of medium voltage networks (22 K.V) and the installation of distribution transformers (22 / 0.4 K.V) to feed factories, firms, institutions, ministries and residence blocks with electricity.

·       GEDCo also finished 2365 minor projects which included low voltage networks to feed houses that are away from the network with electricity.

 

the following table hows the major and minor projects and their cost associated since the establishment of  GEDCo to 31 December 2010

Type of project

Number 

Total cost ($)  

Major Projects

565

12,800,481

Minor Projects

2365

3,857,541

Total

2930

16,658,022

  

2. Develop and increase the efficiency of the network :

The company has executed 993 projects for the purposes of the following:

1.     Installation of new transformers to reduce loads on the existing transformers.

2.     Rehabilitation of old networks and medium-voltage networks to improve network efficiency and reduce losses.

3.     Rehabilitation of low-voltage networks which is old and close to the citizens houses where un-insulated cables has been changed to isolated ABC cables , thus removing away the danger the citizens exposed to ,  reduce losses and solving the problem of voltage drop.

4.     Installation of new medium-voltage networks and transformers in remote areas, which suffer from the problem of very low voltage.

the following table shows the number of projects and associated cost :

 Type of project

Number

Total cost ($)

Development projects , load management and rehabilitation of medium voltage networks

259

6,994,549

Rehabilitation projects for low-voltage networks

734

1,960,108

Total

993

8,954,657

 

3. Energy transportation projects

The company has implemented 46 projects to transport the electrical energy from Gaza Power Generation Plant to the centers of the loads in different governorates. These projects have been funded by the Norwegian government and the Ministry of Finance at a cost of $ 6,285,399.

Type of project

Number

Total cost ($)

linking lines projects

46

6,285,399

 

4. Rural electrification projects :

The company has extended the medium networks voltage networks ( 22 KV ) , low voltage networks  and the installation of distribution transformers in order to deliver electricity supply service to rural areas such as Alfokhari village, Shohada area and Alnasir village , the total cost of the projects is 630,000 US$.

 

To show the networks and transformers that have been added to the network during the period of the company's operations

 

Item

Unit

Quantity

Medium voltage poles

no

1776

Low voltage poles

no

8994

Medium voltage network

m

262066

Low voltage network

m

623757

Distribution transformers (22/0.4 kv)

no

592

Medium voltage disconnectors and breakers

 

no

594

Low voltage distribution switchboards and disconnectors

no

1090

 
 